Project 01 · Big Lake, Texas
Santa Rita Computing. Our first JV, with BitLake.
An energized mining site in Big Lake, Texas, converting to AI capacity with a path to 25 MW.
- 15 MWEnergized today
- +10 MWIn the interconnection queue, targeted for Q3 2027
- 25 MWPlanned campus
At a glance
Power that is already live, and room to grow.
The site starts from an interconnection that is running today, not from a drawing.
Energized today
Interconnected and billed, on the ERCOT grid.
In the interconnection queue
Targeted for Q3 2027, built to AI specification from day one.
Planned campus
Converted in phases, each sized to signed demand.
Energized today
Interconnected and billed today, with no greenfield substation to permit or build before the first racks.
In the interconnection queue
Additional capacity targeted for Q3 2027, to be built to AI specification from day one.
Planned campus
Existing and queued capacity together, converted in phases sized to signed demand.
Transformer zones
A 13.8 kV feed is already on the pad, and transformers T1 to T8 feed zones separately.
The partners
A Texas miner and Chaince Compute, in one JV.
BitLake brings the site and the local know-how. We bring capital, construction and tenants.
Miner partner
BitLake
- Years of local Texas mining experience
- The energized site and power contract
- Local crew and utility relationship
Developer partner
Chaince Compute
- Capital and JV structuring
- The entire construction, delivered turnkey
- AI tenant sourcing and offtake
The joint venture
Santa Rita Computing
- Develops the Big Lake AI data center
- Contracts with AI tenants
- Grows the site toward 25 MW
The model
Offtake first, then a turnkey build.
Tenants bring their own GPUs. The JV provides power, space, cooling and network, built to what they sign.
- 01
Power in place
15 MW is energized and running today.
- 02
JV formed
BitLake and Chaince Compute form Santa Rita Computing.
- 03
Offtake
Large AI tenants that bring their own GPUs sign first.
- 04
Turnkey build
Chaince Compute delivers the facility to the tenant's specification.
- 05
Expand
Queued capacity takes the campus toward 25 MW.
Why this site
The parts that usually take years are already here.
For full specifications and capacity inquiries, visit the Santa Rita Computing website.
santaritacomputing.com- Power you don't wait forThe full 15 MW is interconnected and billed today
- Electrical infrastructure in placeA 13.8 kV feed on site and eight pad-mounted transformer zones
- Fiber on siteConnected today, with room for a second route
- Air or liquid coolingA dry climate suited to dry and evaporative coolers
- Room to grow15 acres, with room to expand
Capacity figures reflect the current site and the utility interconnection queue. Queued capacity and target dates are subject to utility approval, financing and definitive agreements.